Mist Fire Protection for Ayrshire Central Hospital Redevelopment Irvine

Large-Scale Residential Water Mist

High-capacity iCO water mist fire suppression solution protecting 202 new homes on the former Ayrshire Central Hospital site - delivering rapid fire control, minimal water usage, and reduced property damage for a landmark North Ayrshire Council regeneration project.

  • Category
  • ClientAshleigh Construction

Project Details

Project: Ayrshire Central Hospital Redevelopment (Irvine)
Client (Main Contractor): Ashleigh Construction (Scotland) Limited
End Client: North Ayrshire Council
Category: Residential Housing (Houses)
Units: 202
Pump: iCO 202 Pump
Nozzles: 1,888
System: iCO Water Mist
Weblink: [Add link]

Project Overview

Ashleigh Construction (Scotland) Limited has been appointed as the main contractor for a £50 million housing development on the site of the former Ayrshire Central Hospital in Irvine. The project will transform a long-derelict area into much-needed new housing, supporting North Ayrshire Council’s wider programme to improve local housing supply and community outcomes.

The development includes 202 new homes, comprising a balanced mix of general needs housing, amenity bungalows, and wheelchair-accessible properties — helping ensure residents’ needs are met across different life stages and mobility requirements.

Scope, Significance & Programme

Works include the demolition of former maternity residence buildings (with demolition activity beginning in April 2023) to make way for the new homes. The site has held strategic importance locally, having lain increasingly derelict for around 17 years following the relocation of services to Crosshouse Hospital in 2006.

Construction is expected to take approximately two years following the contractor’s appointment in late 2024, with the project supported by Scottish Government funding (reported at around £20m–£24m in public coverage).

NPHS Delivery

NPHS is delivering an iCO water mist fire suppression system across all homes, designed to provide fast-acting, highly effective fire control while using significantly less water than traditional sprinkler solutions — helping minimise disruption, reduce secondary water damage, and support modern residential compliance requirements.

With 1,888 nozzles and an iCO 202 pump configuration, the system has been engineered for reliable protection at scale, supporting a major council-led regeneration and housebuilding programme in North Ayrshire.

 
Ashleigh Construction Project- Central Hospital
Ashleigh awarded £50m contract for Ayrshire Central Hospital site | Scottish Housing News